Time Based Sequential

This plan enables you to schedule multiple activities sequentially. You can choose either the Forward Planning or the Backward Planning option.

  • Forward Planning :On the Gantt chart, select the required multiple activities and using the drag-and-drop option, link the first activity to the required time. Based on the first activity’s planned start time, all the other activities are planned sequentially. You can also modify the planned start time of the first activity, which ensures that all other activities are planned sequentially.
Note: An activity, other than the first activity cannot be selected.
  • Backward Planning: On the Gantt chart, select the required multiple activities and using the drag-and-drop option, link the first activity to the required time. Based on the last activity’s planned finish time, all the other activities are planned sequentially. You can also change the planned finish time of the last activity using the drag-and-drop option. There by ensuring that, from the last activity, all other activities are also planned sequentially. An activity, other than the first activity cannot be selected.