Activities for Corrective Action Plans (tsspc3120m500)
Use this session to view and maintain activities of Corrective Action Plans.
Field Information
- Group
 - 
            
The unique ID of the group.
 - Planning Sequence
 - 
            
The planning sequence of the activity sets for the Corrective Action Plans.
 - Activity Set
 - 
            
The group planning activity set number for the Corrective Action Plans.
 - Start Date Activities
 - 
            
The start date and time of the activities that must be displayed.
 - Finish Date Activities
 - 
            
The finish date and time of the activities that must be displayed.
 - Moved Activities
 - 
            
If this check box is selected, LN displays the activity that have been moved from another group.
 - Allocated Resource
 - 
            
The engineer allocated to the specified group.
 - Activity Set Attributes
 - 
            
The attributes of the activity set.
 - Line
 - 
            
The group planning activity number.
 - Sequence
 - 
            
The group planning activity sequence.
 - Status
 - 
            
The status of the activity.
Allowed values
- Created
 - 
               
The activity is imported from service order activity, work order activity or planned activity. The activity is yet to be planned.
 - Planned
 - 
               
The activity is successfully planned (planning times are updated). The updated start and finish times can be copied to the service order activity, work order activity or planned activity.
 - Not Planned
 - 
               
The activity could not be planned. Owing to failure of the planning process, the activity must be re-planned.
 - Released
 - 
               
The updated start and finish times of the activity are copied to the service order activity, work order activity or planned activity.
 
 - Description
 - 
            
The description or name of the code.
 - Status
 - 
            
The status of the activity.
Allowed values
- Open
 - Approved
 - In Progress
 - Completed
 - Closed
 - Canceled
 
 - Firm Planned
 - 
            
If this check box is selected, the activity is firm planned and you cannot change the start and finish date of the activity.
 - Planned Start Time
 - 
            
The start date and time of the group planning activity.
 - Planned Finish Time
 - 
            
The finish date and time of the group planning activity.
 - Activity Duration
 - 
            
The duration of the Corrective Action Plan activity.
 - Calendar
 - 
            
The calendar that is used to plan Corrective Action Plan related activities.
 - Description
 - 
            
The description or name of the code.
 - Availability Type
 - 
            
The availability type which is used to calculate the start and finish time of the activities to be performed in each location.
 - Description
 - 
            
The description or name of the code.
 - Time Zone
 - 
            
The time zone that belongs to the specified calendar.
 - Description
 - 
            
The description or name of the code.
 - Group
 - 
            
The planning group number from which the activities are originating.
 - Activity Set
 - 
            
The planning activity set number from which the activities are originating.
 - Activity Line
 - 
            
The planning activity number from which the activities are originating.