Update Planned Delivery Times
the ATP Date and/or Planned Available Date are calculated, implying a shortage, the planned delivery date of the order material/part delivery line can be updated with the ATP Date and/or Planned Available Date, using the following options in the Check Material Availability (tstdm2220m000) session:
- Synchronize Materials with Latest Planned Material Line
- Update Planned Delivery Time of Material Lines
- Update Activities and Orders with Latest Planned Material Line
When the Planned Available Inventory is checked and a shortage is identified, Planned Available Date is calculated and this date is used to update the order data. If only a check on the ATP inventory is performed and a shortage is identified, the ATP Date is used to update the order data. If the Update Planned Delivery Time of Material Lines check box is selected, the planned inventory transactions for this material line are updated.
Service/Work Order Resource Planning/Releasing
The three levels of material availability checks can be performed in the Service Order Resource Planning (tssoc2260m000), Release Service Orders (tssoc2200m000) and Plan Work Orders (tswcs3200m000) sessions. Based on the result of these checks, the applicable material availability data is updated in the Service Material Availability (tstdm2520m000) session.
Based on the result, the planned delivery time of the related material lines can be updated and you can also block the order from being planned/released, in case of a material shortage.