To generate service orders for FCOs
Use this process to generate service order for field change order (FCO).
Service Order
For each FCO line that meets your selection criteria, LN generates a service order.
The generated service orders have the following attributes:
- Status is Free.
- Service Type is the value selected in the Service Order Parameters (tssoc0100m000) session.
- Planned Start Time is the Planned Earliest Start Date that you entered in the Field Change Orders (tssoc5100m000) session.
- Planned Finish Time is the sum of all the FCOs reference activity durations added to the Planned Start Time.
- Service department, is copied from the FCO.
- Subcontractor for the service-order activity lines copied from the FCO.
- Activity line data is copied from the FCOs reference activities. The number of service order activities generated for the service order equates to the number of reference activities listed for the FCO.
After you generate a service order from an FCO:
- LN fills the FCO line's Service Order field.
- When you generate the first service orders for an FCO, the FCO's status changes from Lines Generated to Execution.
Note:
LN generates a service order for each
serialized item.