Generate maintenance planning
Use the Generate Maintenance Plan (tsspc2200m000) session to generate maintenance planning. You can plan maintenance activity for the installation group and serialized item that the service organization manages. You can schedule and display the activities in the Planned Activities (tsspc2100m000) session. The maintenance planning provides the maintenance activities that must be carried out in the long term.
The operational planning of the maintenance activities is based on the service order planning. All the operational (service) activities are carried out by means of service orders.
The relative movements are transferred into the actual dates based on the value of the Maintenance Cycle field in the Items - Service (tsmdm2100m000) session. After receiving the start date, the first workable date receives the actual planned start date. The activity duration is added to this date to determine the end date.
To find the first workable date and plan forward, the search path for calendars is:
- The calendar of the serialized item.
- The calendar of the service department that is linked to the Installation group.
Earliest start time = ((Planned start time + Planned end
time)/2)- (Tolerane period x 0.5)
For each planned activity that is generated, the requirement lines are copied from the Resource Requirements (tsacm2120m000) session to one of the following sessions:
- Planned Activity - Material Requirements (tsspc2110m000)
- Planned Activity - Labor Requirements (tsspc2111m000)
- Planned Activity - Other Requirements (tsspc2112m000)
Process Report: List of planned activities generated.
Error Report: List of errors.
Defaults:
- The Date From is the current date.
- The Date To is the current date + one year.