To specify resource requirements
To specify the resource requirements for a reference activity, complete the following steps:
- In the Reference Activity session, select the appropriate reference activity line.
- On the appropriate menu, choose .
- In the Resource Requirements (tsacm2120m000) session, click the Add a New Record button. The details session appears.
- In the Resource Type field, enter one of the following:
- Material
- Labor
- Tool
- Subcontracting
- Other
- Specify other required data.
Note:
If you run the Generate Maintenance Plan (tsspc2200m000) session, the requirement lines that are linked to the reference activity are copied to the following sessions:
- Planned Activity - Material Requirements (tsspc2110m000)
- Planned Activity - Labor Requirements (tsspc2111m000)
- Planned Activity - Other Requirements (tsspc2112m000)
If you run the Transfer Planned Activities to Field Service (tsspc2220m000) session, the requirement lines that are linked to the planned activity are copied to the following sessions:
- Service Order Estimated Material Costs (tssoc2120m000)
- Service Order Estimated Labor Costs (tssoc2130m000)
- Service Order Estimated Other Costs (tssoc2140m000)