Creating a Time Phased Budget (TPB) analysis code

A time phased budget (TPB) comprises of at least two components:

  • A top-down budget version, maintained in the Budget Version (tpptc5100s000) session.
  • A top-down budget TPB analysis code.
  1. Create a TPB analysis code using the Time Phased Budget Analysis Codes by Project (tpptc5120s000) session or generate the TPB code using the Generate Time-Phased Budget (tpptc5200m000) session.
  2. Link a top down budget version to the TPB analysis code using the Budget Version (tpptc5100s000) session.
  3. Specify the permitted baseline status value(s) to be used for performance measurement in the Time Phased Budget Analysis Codes by Project (tpptc5120s000) session.
  4. Link the TPB analysis code to the project. This code can be used to compare the various TPBs using the Time Phased Budget (tpptc5821m000) session.
    Note: The details that you specify in the Time Phased Budget Analysis Codes by Project (tpptc5120s000) session, are the default values for the Generate Time-Phased Budget (tpptc5200m000) session. If you change the values in the Generate Time-Phased Budget (tpptc5200m000) session, Infor LN updates the data in the Time Phased Budget Analysis Codes by Project (tpptc5120s000) session after the time-phased budget is generated.