EV Milestones Related Data (tpptc5111s000)
Use this session to maintain the amount or percentage associated with a selected milestone. You can enter the amount or percentage at milestone level, or by cost type within a milestone.
You must specify the project and the time phase budget version of the milestone.
Field Information
- Project
-
The code that uniquely identifies the project.
- Description
-
The description or name of the code.
- Project Status
-
The project status.
- Current Version
-
You can enter data in this version for this project.
- Activity
-
The code that uniquely identifies the activity.
- Description
-
The description or name of the code.
- Status
-
The budget status of the activity.
- Milestone
-
The code that uniquely identifies the milestone.
- Budget Status
-
The budget status.
- Version
-
The version in which the data of the activity is stored.
- Currency
-
The code that uniquely identifies the currency.
- Milestone Amount
-
The amount of the milestone.
- Remainder Activity Amount
-
The remaining activity amount. This is the undistibuted amount of the parent activity or if the element is the TOP activity the amount is the version amount.
- Milestone Percentage
-
The percentage of the budget that you want to release, the so called budgeted costs of work scheduled.
- Text
-
If this check box is selected, the activity has an associated text, which you can view by clicking the Text button on the toolbar.
- Material Amount
-
The budgeted amount of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
- If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
- Material %
-
The budgeted percentage of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
- Labor Amount
-
The budgeted amount of the labor cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
- If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
- Labor %
-
The budgeted percentage of the labor cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
- Equipment Amount
-
The budgeted amount of the equipment cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
- If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
- Equipment %
-
The budgeted percentage of the equipment cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
- Subcontracting Amount
-
The budgeted amount of the subcontracting cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
- If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
- Subcontracting %
-
The budgeted percentage of the subcontracting cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
- Sundry Cost Amount
-
The budgeted amount of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
- If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
- Sundry Costs %
-
The budgeted percentage of the sundry cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).