EV Milestones Related Data (tpptc5111s000)
Use this session to maintain the amount or percentage associated with a selected milestone. You can enter the amount or percentage at milestone level, or by cost type within a milestone.
You must specify the project and the time phase budget version of the milestone.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Description
 - 
            
The description or name of the code.
 - Project Status
 - 
            
The project status.
 - Current Version
 - 
            
You can enter data in this version for this project.
 - Activity
 - 
            
The code that uniquely identifies the activity.
 - Description
 - 
            
The description or name of the code.
 - Status
 - 
            
The budget status of the activity.
 - Milestone
 - 
            
The code that uniquely identifies the milestone.
 - Budget Status
 - 
            
The budget status.
 - Version
 - 
            
The version in which the data of the activity is stored.
 - Currency
 - 
            
The code that uniquely identifies the currency.
 - Milestone Amount
 - 
            
The amount of the milestone.
 - Remainder Activity Amount
 - 
            
The remaining activity amount. This is the undistibuted amount of the parent activity or if the element is the TOP activity the amount is the version amount.
 - Milestone Percentage
 - 
            
The percentage of the budget that you want to release, the so called budgeted costs of work scheduled.
 - Text
 - 
            
If this check box is selected, the activity has an associated text, which you can view by clicking the Text button on the toolbar.
 - Material Amount
 - 
            
The budgeted amount of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
 - If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
 
 - Material %
 - 
            
The budgeted percentage of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
 - Labor Amount
 - 
            
The budgeted amount of the labor cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
 - If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
 
 - Labor %
 - 
            
The budgeted percentage of the labor cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
 - Equipment Amount
 - 
            
The budgeted amount of the equipment cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
 - If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
 
 - Equipment %
 - 
            
The budgeted percentage of the equipment cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
 - Subcontracting Amount
 - 
            
The budgeted amount of the subcontracting cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
 - If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
 
 - Subcontracting %
 - 
            
The budgeted percentage of the subcontracting cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).
 - Sundry Cost Amount
 - 
            
The budgeted amount of the material cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the amount entered in the field Milestone Amount.
LN issues a warning message, which you can accept or ignore, in the following cases:
- If the cost type amount, together with other child amounts of the cost type, does exceed the budgetted parent amount of the cost type (taking any currency conversions into account).
 - If the total cost type amount from the childs of this activity exceeds this cost type amount (taking any currency conversions into account).
 
 - Sundry Costs %
 - 
            
The budgeted percentage of the sundry cost-type assigned to the milestone. The currency of the amount is the same as the currency of the milestone, and the default value is 20% of the figure entered in the field Milestone %.
LN issues a warning message, which you can accept or ignore, if the amount, together with other child amounts, exceeds the budgeted amount of the parent (taking any currency conversions into account).