Purchase Budget Parts (tpptc4510m000)

Use this session to list the broad parts of the purchase budget.

Field Information

Project

The code that uniquely identifies the project.

Project Status

The project's status.

Code Origin

The code identifies the 'part' within the budget level on which the purchase budget is based.

Code Origin

The code origin.

Purchase Budget

The code that uniquely identifies the purchase budget.

Purchase Budget Status

Purchase budget status.

Budget Amount

The total budget amount of the purchase budget.

Currency

The currency used to express the budget amount.

Sequence Number

The code that uniquely identifies the sequence number.

Budget Type

The type of budget the purchase budget line relates to.

Cost Type

The cost-type of the purchase budget line.

Cost Object

The cost object on the purchase budget line.

Percentage

That part of the actual budget line amount which is included in the purchase budget part.

Example

Actual budget line:

100 units x 200 = 20,000

Purchase budget part:

100 units x 200 x 50 (%) / 100 = 10,000