Delete Budget (tpptc2203m000)
Use this session to delete the bottom-up budget lines for a range of elements or activities of a project. You can only delete the budget lines based on the status of the project , budget status, and budget adjustments. The report includes the deleted budget lines and the lines that are not deleted, and the reason for the deletion.
Example
- Generate Budget Cost Analysis (tpptc3200m000)
 - Generate Control Data (tpptc1230m000)
 
Field Information
- Selection Range
 - 
            
- Selection Range
 - 
                     
Use the fields in the Selection Range to specify the range of data for which you want to delete the budget lines.
 
 - Structure Range
 - 
            
- Elements
 - 
                     
If this check box is selected, the From and To fields related to the elements are enabled.
 - From
 - 
                     
The From and To fields define a range of: elements for which you want to delete the budget lines.
 - Activities
 - 
                     
If this check box is selected, the From and To fields related to the activities are enabled.
 - From
 - 
                     
The From and To fields define a range of: activities for which you want to delete the budget lines.
 
 - Reports
 - 
            
- Process Report
 - 
                     
If this check box is selected, LN prints the process report for the selected range of data.
 - Error Report
 - 
                     
If this check box is selected, LN prints the error report for the selected range of data.
 
 - Cost Object
 - 
            
- Cost Object Selection
 - 
                     
- Item
 - 
                              
If this check box is selected, the From and To fields related to the item are enabled.
 - From
 - 
                              
The From and To fields define a range of: items for which you want to delete the budget lines for the specified elements or activities.
 - Labor
 - 
                              
If this check box is selected, the From and To fields related to the labor are enabled.
 - From
 - 
                              
The From and To fields define a range of: labor lines for which you want to delete the budget lines for the specified elements or activities.
 - Equipment
 - 
                              
If this check box is selected, the From and To fields related to the equipment are enabled.
 - From
 - 
                              
The From and To fields define a range of: equipments for which you want to delete the budget lines for the specified elements or activities.
 - Subcontracting
 - 
                              
If this check box is selected, the From and To fields related to the subcontracting are enabled.
 - From
 - 
                              
The From and To fields define a range of: subcontracting lines for which you want to delete the budget lines for the specified elements or activities.
 - Sundry Cost
 - 
                              
If this check box is selected, the From and To fields sundry cost are enabled.
 - From
 - 
                              
The From and To fields define a range of: sundry-cost lines for which you want to delete the budget lines for the specified elements or activities.