Control Data for Physical Progress (Labor Lines) (tpptc1546m000)
Use this session to display budget lines from the control budget for the labor cost-type
These lines are used for progress registration.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Description
 - 
            
The description or name of the code.
 - Project Status
 - 
            
The project status.
 - Element
 - 
            
The code that uniquely identifies the element.
 - Description
 - 
            
The description or name of the code.
 - Budget Status
 - 
            
The budget status of the element.
 - Plan
 - 
            
The code that uniquely identifies the plan.
 - Activity
 - 
            
The code that uniquely identifies the activity.
 - Description
 - 
            
The description or name of the code.
 - Budget Status
 - 
            
The budget status of the activity.
 - Task
 - 
            
The code that uniquely identifies the labor.
 - Description
 - 
            
The description or name of the code.
 - Sequence Number
 - 
            
The code that uniquely identifies the sequence number.
 - Work [%s]
 - 
            
The number of hours for the labor line.
 - Currency
 - 
            
The home currency for the cost amount.
 - Cost Amount
 - 
            
The labor costs in the control data.
 - Cost Amount [%s]
 - 
            
The amount in the home currency.
 - Cost Component
 - 
            
The code that uniquely identifies the cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Control Code
 - 
            
The code that uniquely identifies the control code.
 - Extension
 - 
            
The code that uniquely identifies the extension.