Cost Details Element Budget (Material) (tpptc1123m000)

Use this session to maintain the cost details of the element budget (material) lines.

Note: 

The data in this session is defaulted from the Element Budget (Material) (tpptc1110s000) session if while generating budget the option Cost Component has been used. You can only modify the value in the Amount field.

Field Information

Item

The item linked to the element.

Description

The description or name of the code.

Effectivity Unit

The effectivity unit applicable for the item.

Description

The description or name of the code.

Budget Line

The line number of the element budget.

Currency

The currency of the element budget.

Total Cost Details

The sum of all the cost detail amounts for the element budget.

Note: If you modify the value in the Amount field, Infor LN recalculates this value.
Difference

The difference between the unit cost of the item and the amount per unit in the cost details of the element budget line.

Note: If you modify the value in the Amount field, Infor LN recalculates this value.
Cost Component

The cost component linked to the element budget. For each of the cost components present for an item a corresponding line is displayed.

Description

The description or name of the code.

Cost Component Type

The type of cost component that is linked to the element budget.

Allowed values

Detail

Used to collect costs defined for the specified cost component.

Optional for a valid cost component scheme.

Collect

Used to define costs or rates that are not specifically defined in the cost component scheme. None-specific costs are collected on the related collect cost component.

Note: A valid cost component scheme must have one cost component of the type Collect with the General Costs.
Aggregated

Used to aggregate detail and collect cost components by type: materials, operations, surcharges and general. Each cost component scheme must have an aggregate cost component for each of the types.

Note: A valid cost component scheme must have aggregated cost components specified for all four component types.
Amount

The total amount of the element budget.

Currency

The currency in which the amount for the element budget is specified.