Budget Cost Surcharges by Cost Component (tpptc0527m000)
Use this session to display for a selected project the cost surcharges that are based on the budget lines of a specific cost component.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Project Status
 - 
            
The status of the project.
Allowed values
- Free
 - Active
 - Finished
 - Closed
 - Archived
 
 - Sundry Cost
 - 
            
The code that uniquely identifies the sundry costs.
 - Description
 - 
            
The description or name of the code.
 - Cost Component
 - 
            
The code that uniquely identifies the cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Sequence Number
 - 
            
The code that uniquely identifies the sequence number.
 - Percentage
 - 
            
The surcharge percentage specified for the cost to calculate the surcharge amount.
 - Budget Status
 - 
            
The status of the surcharge.
Allowed values
- Free
 - 
               
You can modify all the data.
 - Actual
 - 
               
You can modify the budget data and generate the control data. You can also log the budget history.
 - Final
 - 
               
You cannot modify the budget data. You can only add or modify the budget lines using a budget adjustment. You can also log the actual budget history.
 
 - Element
 - 
            
The code that uniquely identifies the element.
 - Activity
 - 
            
The activity to which the surcharge is posted.