Budget Cost Surcharges by Cost Type (tpptc0126s000)
Use this session to maintain cost surcharges by cost-type for the selected element, cost component or extension.
You can create surcharges only for projects that have a Free or Active project status.
The surcharge is based on the budget lines in which the selected cost type is used.
Field Information
- Project
 - 
            
The code that uniquely identifies the project.
 - Description
 - 
            
The description or name of the code.
 - Project Status
 - 
            
The project's status.
 - Sundry Cost
 - 
            
The code that uniquely identifies the sundry costs cost object.
 - Sundry Cost
 - 
            
The type of reference.
 - Sequence Number
 - 
            
The code that uniquely identifies the sequence number.
 - Percentage
 - 
            
The surcharge percentage calculated on the budgeted costs for material.
This calculation is based on the following formula:
(percentage/100) * budgeted costs for the material on a single lineThe surcharges are not included in the budgeted costs (a surcharge is not calculated on another surcharge).
If you select an extension, the computation is as follows:
(percentage/100) * budgeted costs of extension (Material cost-type) - Status
 - 
            
The status of the budget.
 - Effective Date
 - 
            
The date on which the surcharge takes effect. This date is compared with the project start date in order to define whether the surcharge applies or not.
 - Expiry Date
 - 
            
The date on which the surcharge expires. This date is compared with the project start date in order to define whether the surcharge applies or not.
 - Element
 - 
            
The code that uniquely identifies the element. If you select an element in this field, the surcharge amount is posted to that element.
If you perform a budget-cost analysis and generate control data for all elements, LN calculates the surcharge percentage on the direct costs for each element, and posts it to that element.
 - Description
 - 
            
The description or name of the code.
 - Plan
 - 
            
The code that uniquely identifies the plan. The plan includes the activity to which the surcharge is posted.
 - Activity
 - 
            
The activity that the surcharge is posted to.
If you perform a budget-cost analysis and generate control data for all activities, LN calculates the surcharge percentage on the direct costs for each activity, and posts it to that activity.
 - Description
 - 
            
The description or name of the code.
 - Cost Component
 - 
            
The code that uniquely identifies the cost component.
Note: You can only specify a cost component for which the Component Type is set to Detail or Collect in the Cost Components (tcmcs0148m000) session. - Extension
 - 
            
The code that uniquely identifies the extension. If you select an extension, the surcharge is applied to, and posted to, that extension.
 - Description
 - 
            
The description or name of the code.
 - Extension Type
 - 
            