External Scheduling Calendars (tppss2132m000)

Use this session to view calendar related project data that is linked to the external scheduling package.

Note: 

The data in this session is populated from the External Scheduling Interface (tppss2231m000) session, when you import/ export the Infor LN project data from/ to an external scheduling interface.

Field Information

Project

The code of the project for which the external scheduling package is used.

Description

The description or name of the code.

Plan

The plan that must be used for the import or export of the project data to or from an external scheduling package.

Description

The description or name of the code.

Connection Node

The activity or node of the Infor LN Project (related to calendar) that must be connected to the activity or node of a project in the external scheduling package. If you link a complete project in Infor LN to a project in the external scheduling package, this node is not specified.

Description

The description or name of the code.

Calendar

The code of the calendar used by the external scheduling package.

Description

The description or name of the code.

Availability Type

The availability type used by the external scheduling package.

Description

The description or name of the code.

Last Refresh Date

The date and time when the Infor LN Project data is last synchronized with the external scheduling package.

ESP Reference

The reference number linked to the external scheduling package (ESP).

Synchronization Status

The status of the synchronization of the Infor LN project data with the external scheduling package.

Allowed values

Synchronized
Delete
Modify
New
Initial