Plans (tppss0110m000)

Use this session to view and maintain the plans for a project.

Note: You can only make a plan active when the plan has an activity structure.

Field Information

Project

The code that uniquely identifies the project.

Description

The description or name of the code.

Project Status

The current project's status.

Plan

The code that uniquely identifies the plan.

Description

The description or name of the code.

Planner

The code that uniquely identifies the planner.

Name

The name of the planner.

Top Activity

The code that uniquely identifies the top activity of the structure.

This is either defined when:

  1. You enter the first activity in the Activities (tppss2100m000) session or
  2. You change or insert the top activity in the appropriate menu option.
Description

The description or name of the code.

Update Mode

The update mode specified for the Project/Plans. If the value of the field is set to Read-only, network planning is not applicable for the Project/Plans.

Allowed values

Update

The plan can be updated via the Generate Budget Cost Analysis (tpptc3200m000) session.

Read-only

The plan can no longer be updated via the Generate Budget Cost Analysis (tpptc3200m000) session. Select Read-only to prevent an initial budget or a specific budget version from being overwritten. This allows you to compare two budget-cost analysis versions via the Compare Budget Cost Analysis (tpptc3420m000) session.

Scheduled Start Date

This identifies the plan's start date and time.

Scheduled Finish Date

This identifies the plan's end date and time.

Active Plan

If this check box is selected, this plan is the active plan. It can be used to create a budget, to monitor costs and progress. The plan can only become Active if you created an activity structure.

If this check box is cleared, this plan can only be used for simulating a budget or for scheduling activities.

Text

If this check box is selected, a text is present.