Control by Project/Extension (tpppc4530m000)

Use this session to monitor the projects that are executed. The actual cost control is aggregated at the project/extension level in this session.

This is one in a range of sessions that are available in the Project Progress module for monitoring projects. Each of these sessions provides a different level of detail.

Field Information

Project

The code that identifies the project.

Currency

The default currency in the overview session is the project currency. Both in a dependent and in an independent currency system you can change this currency to other currencies with the Rotate Currency option <CTRL-R>.

The following sequence is applicable:

  1. Project currency
  2. Local currency
  3. Reporting currency 1
  4. Reporting currency 2
Note: Only the last three currencies are home currencies.
Currency

The currency.

Generated

The date on which the current project cost control was built. The value of this field is updated by the Build Actual Cost Control (tpppc4803m000) session.

Extension

extension

Total Budget

The budgetted amount as shown in the control data.

Earned Value

The costs allowed at the end of the current period.

Revenues

The revenues posted to the history for all periods up to the current one.

Current Period

The year of the actual cost control period.

/

The period for actual cost control

Incl. Commit. Earned Value

The costs that can be incurred in the current period.

Excl. Commit Actual

The actual costs (so without the commitments) posted to the history for the current period.

Excl. Commit. Earned Value

The allowed amount excluding commitments.

Revenues

The revenues in the current period which have been posted to the history.