Cost Forecast by Activity/Cost Type (tpppc2126m000)

Use this session to maintain the cost forecast for the combination of project, registration date, and activity for the different cost types. This data is used to calculate the extra costs and estimate to complete or estimate at completion amount in the performance measurement sessions.

Field Information

Project

The project code for which the cost forecast is maintained.

Description

The description or name of the code.

Project Status

The project status of the project for which the cost forecast is maintained.

Registration Date

The date of input for the forecast deviation of costs. Based on the registration date, Infor LN determines on which actual transaction must be considered for the calculation of the forecast. For example, if there are two actual cost transactions with date October 15 and another with October 20 and the specified registration date of the forecast is before October 20 and after October 15, the one with date October 20 is ignored.

Activity

The activity code for which the cost forecast is maintained.

Description

The description or name of the code.

Currency

The currency in which the cost forecast is maintained.

Currency Rate/Rate Factor

The currency rate that is used to convert the transaction currency to the home currency.

Rate Factor

The rate factor that belongs to the currency rate which is displayed.

12345678901234567890

The estimate to complete amount needed for the item cost type to finish the project.

12345678901234567890

The estimate to complete amount needed for the labor cost type to finish the project.

12345678901234567890

The estimate to complete amount needed for the equipment cost type to finish the project.

12345678901234567890

The estimate to complete amount needed for the subcontracting cost type to finish the project.

12345678901234567890

The estimate to complete amount needed for the sundry cost's cost type to finish the project.

Home Currency

The cost amount in the home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The amount of the material in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The amount of the labor in the home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The amount of the equipment in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The amount of the subcontracting in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The amount of the sundry cost in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The estimate at completion amount for the material cost type.

12345678901234567890

The estimate at completion amount for the labor cost type.

12345678901234567890

The estimate at completion amount for the equipment cost type.

12345678901234567890

The estimate at completion amount for the subcontracting cost type.

12345678901234567890

The estimate at completion amount for the sundry cost type.

12345678901234567890

The cost of the material in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The cost of the labor in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The cost of the equipment in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The cost of the subcontracting in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The cost of the sundry cost in home currency. Click Rotate Currency to see the amount in the other home currencies.

12345678901234567890

The actual amount for material cost type.

12345678901234567890

The actual labor amount.

12345678901234567890

The actual equipment amount.

12345678901234567890

The actual subcontracting amount.

12345678901234567890

The actual sundry cost amount.

12345678901234567890

The budgeted amount for the material cost type .

12345678901234567890

The budgeted labor amount.

12345678901234567890

The budgeted equipment amount.

12345678901234567890

The budgeted subcontracting amount.

12345678901234567890

The budgeted sundry cost amount.

Currency

The estimate at completion amount in home currency.