Update Planned Delivery Dates (tppdm7200m200)

Use this session to update the planned delivery dates of the deliverable and deliverable schedules, for a specified range of data, based on the scheduled dates of milestones or work packages using the latest scheduling results for the execution of the logistics.

Using this session, you can generate a 'Changed Planned Delivery Dates' report that displays the old and the updated delivery dates of the deliverables and the deliverable schedules for the specified range of data.

Note: 

You can update the planned delivery date for the contract deliverables and deliverable schedules only if:

  • the status of the deliverable or the schedule is set to Free, Active, or Released to Warehousing.
  • the Return Deliverable check box in the Contract Deliverables (tppdm7100m100) or the Contract Deliverables Schedule (tppdm7100m200) session is not selected.

The new planned delivery date can be based on the:

  • scheduled finish date of the milestone (if defined for the contract deliverable).
  • scheduled finish date of the activity (if defined for the contract deliverable and if the activity is of the type Work Package).

Field Information

From Delivery Date

The date from which all the planned delivery dates must be updated. By default, the current date is displayed. However, you can set this field to a date later than or prior to the value specified in the Planned Shipping Date field in the Contract Deliverables (tppdm7100m100) session.

Note: For example, if the current date is 24/4/2017 and the contract has two deliverables linked, one for 25/04/2017 and the other for the 23/04/2017, you must set this date to 22/04/2017 or earlier to include and update all the deliverable dates later than or prior to the date.
Process Report

If this check box is selected, LN prints the process report for the specified range of data.