To structure the estimate

To create an estimate, the structural element with a top-down leading estimate type is required. In the Structural Element session, you can define the estimate type as top down or bottom up. The leading estimate type of a structural element determines the method of calculation of the estimate and you can also modify the estimate type.

Enter your top-down estimate in the Estimate Lines (tpest2100m000) session such as the line number, activity, description, estimate type, line level type, and amount in EURO.

Line 5 TOP Yacht Top down Total 60 million
Line 10 01 Redesigning Top down Total 9 million
Line 20 02 Building ship Top down Total 50 million
Line 25 03 Decorating Top down Total 1 million

Element 03, Line 25, is subcontracted to another company. A request for a quotation is sent to the subcontractor, but the estimate for the cost is EURO 1 million.

Estimate lines

You must specify detailed estimate lines and you must define the entire estimate structure. Child activities, for which more bottom-up information is available, use the Bottom-Up leading estimate type option:

Structural Element LET Launch Level Type Cost Level Type Sales Level Type
TOP = The yacht top down detail total total
01 = Redesigning top down detail total total
02 = Building top down detail total total
03 = Decorating top down detail total total
011= CAD rework top down detail total total
021= Steel bottom up detail detail total
022= Yard work bottom up detail detail total
023= Engine bottom up detail detail total

The structural element 011 is linked to 01. The structural element 021, 022, and 023 are linked to 02. Based on the linking, the 02 Building ship parent activity remains a top-down activity because of expected overhead costs.

Line number Activity Estimate Type Line Level Type Amount in EURO
30 021 top down total 30 million
35 022 top down total 15 million
40 023 top down total 2 million
45 011 top down total 5 million
50 011 top down detail 3 million
55 011 top down detail 2 million
60 02 top down cost type (labor) 4 million
65 02 top down cost type (material) 46 million

Estimate details

In the example, a top-down estimate is used and amounts are allocated. However, the two internal departments involved in this project provide their own estimates for building the yacht. Based on their evaluation, they provide a more detailed calculation. Specify these lines and the related details in the estimate version.

Line number Activity Estimate Type Line Level Type Amount in EURO
70 011 bottom up total 5 million
80 011 bottom up detail 2.7 million for engineering
81 011 bottom up detail 0.3 million for project management
85 023 bottom up detail 1 million
90 022 bottom up detail 15 million
95 021 bottom up total 40 million
100 03 bottom up detail 0.5 million

If you view the details of the activity 011, a top-down total of EURO 5 million is expected. However, if you add the two bottom-up detail lines of 011, that part of the ship adds up to EURO 3 million or 5 million, depending on the Line Level Type. If all required estimate lines are specified, you can aggregate the totals and view the estimate amounts for the leading estimate type. For the formulas, refer to Estimate Lines (tpest2100m000) session.