Job Shop Planning Board Workbench Gantt

The Gantt section of the Job Shop Planning Board (tisfc8372m000) allows you to view the scheduled operations.

You can select Production Order tab to view the operations grouped by production orders in the Gantt. You can select the Schedule View tab to view the operations grouped by Work Centers and Machines (Machine Types) in the Gantt.

These context actions are available:

  • Gantt: Create Production Order, Job Shop Schedule Runs.
  • Production Order: Release, Reschedule, Report Order Complete, Pegging-Upstream, Pegging-Downstream, Transfer Planned Production Orders, Print Production Order Documents.
  • Operation: Report Operation Complete, Drag and Drop of an operation to change operation time, Machine Availability to record Machine Breakdown time of an operation. The Fix dates for Planning and Scheduling to select the Fixed Planning Dates for an Operation, and the Locked for Scheduling for a Machine Operation.
Note: 
  • If the Job Shop by Site field is set to Inactive, the menu title is Fix dates for Planning.
  • The lock symbol is displayed on the Operation, if a flag is selected.