Generating Work Center Input/Output Control
The data LN generates is determined by the following fields in the Production Order Parameters (tisfc0100s000) session:
- Update Method I/O Control: determines whether the target period is a number of weeks or a number of days.
 - No. of Periods to Generate I/O Data: determines how many days or weeks the target period contains.
 - Include Partial Completions (Default): determines whether or not LN must take into account routing operations that are only partially completed to calculate input / output values.
 
Note: For a work center to be taken into account for input/output
		  control, you must select the Critical in Master Planning check box in the Work Centers (tirou0101m000) details session.
      Related sessions
- You can delete data which you no longer require with the Delete Work Center Input/Output Control (tisfc3212m000) session.