Order Block Sequencer (tisfc4220m000)
Field Information
- Site
 - 
            
The site for which the machine operations are sequenced.
 - Plan Group
 - 
            
The plan group to which machine operations are sequenced.
 - Work Center
 - 
            
The work center within the plan group for which the machine operations are sequenced.
 - Machine Type
 - 
            
The machine type within the plan group for which the machine operations are sequenced.
 - Machine Number
 - 
            
The machine number within the plan group for which the machine operations are sequenced.
 - Start Date
 - 
            
The date the first sequenced machine operation is scheduled to start.
 - Horizon Date
 - 
            
The last date for which machine operations are obtained for sequencing. The original planned finish date of the machine operation is used as a selection criterium.
 - Exclude Orders of previous Block Runs
 - 
            
If this check box is selected, machine operations that have been sequenced in previous runs are excluded from sequencing.
 - Delete previous Block Runs
 - 
            
If this check box is selected, the previously sequenced block runs are deleted.
 - Automatic Update Production Orders
 - 
            
If this check box is selected, the production orders the machine operations belong to are automatically updated after sequencing.