Machine Utilization Chart (tisfc1511m000)

Use this session to generate a chart in which you can view the utilization of a specific machine for a specific period of time. The chart displays the total available machine hours as well as the total required machine hours.

LN calculates the total available machine hours of the machine using the calendar of the work center to which the machine is linked. If the chart does not display the total available hours, it means that the machine is not linked to a work center.

LN takes several order types into account to calculate the total required machine hours:

  • Planned production orders in Enterprise Planning
  • SFC production orders that are not Completed or Closed
  • Service orders and maintenance orders

You can select the following check boxes to indicate that the capacity for a specific order type must be displayed in the chart:

  • Show capacity used for planned production orders
  • Show capacity used for production orders
  • Show capacity used for service and maintenance orders

You can also find information about machine utilization in the following sessions:

  • Machine Utilization by Day (tisfc1505m000)
  • Machine Utilization by Week (tisfc1504m000)
Note: The chart cannot display the machine utilization for a specific PCS project.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Machine

machine

Period Length

The period length (in days) for which LN calculates the machine utilization.

Allowed values

  • 1 Day
  • 7 Days
  • 14 Days
  • 28 Days
Start Date

The start date of the first period for which LN calculates the machine utilization.

Number of Periods on Chart

The number of periods for which LN calculates the machine utilization.

Number of Periods in View

The number of periods that is displayed in the chart.

If LN calculates the machine utilization for more periods than displayed in the chart, you can click Next Records in the chart to view the other periods.

Show capacity used for planned production orders

If this check box is selected, the machine capacity that is required for planned production orders is displayed in the chart.

Show capacity used for production orders

If this check box is selected, the machine capacity that is required for SFC production orders is displayed in the chart.

Show capacity used for service and maintenance orders

If this check box is selected, the machine capacity that is required for service orders and maintenance orders is displayed in the chart.

Graph Type

The type of chart that is displayed.

Allowed values

  • 2D Bar Graph
  • 3D Bar Graph