Material Costs (tirpt7520m100)
Use this session to view the estimated material costs per cost document.
Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Cost Document
 - 
            
The work cell cost document number for which the material is costed.
 - Production Model Status
 - 
            
The cost document status.
Allowed values
- Open
 - 
               
Costs can be added to the cost document.
 - Closed
 - 
               
Costs can no longer be added to the cost document.
 - Initial
 - 
               
The cost document has been generated, but no costs have been added.
 
 - Start Date
 - 
            
The first date from which costs are booked on the specified cost document.
 - Work Cell
 - 
            
The work cell the cost document is linked to.
 - End Date
 - 
            
The last date costs are booked on the specified cost document.
 - Calculation Date
 - 
            
The date when the cost estimates are calculated.
 - Material
 - 
            
item
 - Estimated Cost
 - 
            
The estimated material cost of the product.
 - Registered Cost
 - 
            
The material costs of the product manufactured in the period the cost document has been active.
 - Expected Cost
 - 
            
The material costs expected by the end of the cost document period.
 - Actual Cost
 - 
            
The actual material costs registered from the start of the cost document.
 - Estimated Quantity
 - 
            
The estimate of the quantity product manufactured in the period the cost document is active.
 - Registered Quantity
 - 
            
The part of the estimated quantity that has been reported completed.
 - Expected Quantity
 - 
            
The quantity of product expected to be manufactured.
 - Actual Quantity
 - 
            
The quantity of product already issued, or received by the specified warehouse.
 - Estimated Hours
 - 
            
The estimated number of production hours required to complete cost document.
 - Registered Hours
 - 
            
Part of the estimated hours that have been used for manufacture.
 - Expected Hours
 - 
            
The estimated hours still free for use.
 - Actual Hours
 - 
            
The hours booked on the cost document.