Backflush Schedule Line Materials (tirpt4221m100)
Use this session to manage the issuing of backflush schedule line materials.
Note: Blackflushing is done on reporting end items complete, at the
		  closing of a shift, the closing of a work cell cost document or manually
		  done.
Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Production Schedule
 - Schedule Position
 - 
            
The material's position in the production schedule.
 - Work Cell
 - To Date/Time
 - 
            
The date and time to which schedule line materials are issued.
 - Backflush Sequence
 - 
            
The sequence in which LN backflushes materials for schedule lines.
 - Print Report
 - 
            
If this check box is selected, a material issue report is printed.
 - Print errors only
 - 
            
If this check box is selected, a report of the material issue errors is printed.