Close Production Schedules (tirpt4201m000)

Use this session to close a range of production schedule (lines).

Note: This session validates the status of material lines in the selected production order lines for the production schedule.

Field Information

Site

The site ID.

Note: Only visible if multisite functionality is active.

Production Schedule

The ID of the schedule.

Note: The value is defaulted from the Production Schedules (tirpt4101m000) session.
Schedule Position

The ID of the production schedule line.

Note: The value is defaulted from the Production Schedule Lines (tirpt4102m000) session.
Schedule Lines Only

If this check box is selected, the open material lines for the selected range of production schedule lines are closed.