Work Cell Planning (tirpt4102m200)
Use this session to view the planned schedule lines for a work cells.
Field Information
- Work Cell
- Repair Cell
-
If this check box is selected, a repair cell is linked to the selected work cell.
- Planned Start
-
The production start date of a schedule line.
- Schedule
-
The production plan with time phased production quantities for an item or set of items that are built together according to a production model.
- Line
-
The schedule line number.
- Product
-
The repetitive item that is reported.
- Quantity Ordered
-
The total quantity to be produced for the schedule line.
- Duration [Hrs]
- Quantity to Backflush
-
The quantity to be backflushed based on the delivered quantities for the schedule line.
- Quantity Backflushed
-
The produced quantity for which the required materials are backflushed.
- Original Start Date
-
The earliest date materials to manufacture the item are available.
- Original Finish Date
-
The earliest date the planned quantity can be completed.
- Production Finish Date
-
The date on which the production order is completed.
- Actual Start
-
The actual date on which manufacture of the items for production is started.
- Actual Finish
-
The actual date on which manufacture of the items for production is completed.
- Origin
-
The origin of the production run.
Allowed values
- Planning
-
The production run is scheduled using Enterprise Planning .
- Manual
-
The production run is scheduled manually.
- Status
-
The status of the production run.
Allowed values
- Free
-
Run schedule is controlled by the planning engine.
- Released
-
Run schedule complete, changes can only be made manually.
- Active
-
Production run schedule is being implemented.
- Production Completed
-
All schedule lines for the production run were completed, but the run has not been closed.
- Completed
-
All schedule lines for the production run were completed, and all completed products were delivered into inventory. You can still account hours and issue materials for the run schedule.
- Closed
-
The run schedule was completed, changes can no longer be made.
- Warehousing Order
-
The ID of the warehouse order related to the production run.
- Quantity Completed
-
The quantity product reported Completed.