Operation Cost Analysis (tirou4101m100)
Use this session to display the calculated operation costs by routing operation, along with the level at which the retrieved rates are defined.
Field Information
- Product
 - 
            
The product ID.
 - Site
 - 
            
The site for which the routing is defined.
 - Routing
 - Revision
 - 
            
The routing revision to which the related routing operation applies.
 - Reference Date
 - 
            
The date used to retrieve the date effective, approved operation rates used in the calculations.
 - Cost Calculation Code
 - Order Quantity
 - 
            
The amount of product to be purchased or manufactured at one time. In case of a customized item, the total required quantity as specified in the project structure.
 - Status
 - 
            
The status of the routing.
 - Operation Rate Currency
 - 
            
The currency automatically selected for the specified rates for the site.
 - Effective Date
 - 
            
The date he routing revision becomes effective.
 - Expiry Date
 - 
            
The date the routing revision expires.
 - Operation
 - 
            
The operation ID.
 - Reference Operation
 - 
            
The ID of the task performed on the manufacturing machine.
 - Machine Type
 - 
            
The sort of machine that is used during production.
 - Number of Machines
 - 
            
The number of machines used during production.
 - Labor Resources for Production (FTE)
 - 
            
The number of man hours needed for production.
 - Labor Resources for Setup (FTE)
 - 
            
The number of man hours needed to setup for production.
 - Work Center
 - Setup (h)
 - 
            
The operation setup time in hours.
 - Run (h)
 - 
            
The operation cycle time in hours, multiplied by the quantity in the Order Quantity field.