Generate Network Planning (tipcs4210m000)
Use this session to generate network planning by project in which the following is determined:
- The planned start and finish dates of activities.
 - The rough capacity requirements for each activity.
 - The planned start and completion dates of the projects.
 - In case of a main project the planned start and finish dates of the sub-project activities.
 
Field Information
- Project