Print Posted Production Results by Work Center (ticst1401m000)
Use this session to print production results for a range of work centers.
Field Information
- Site
 - 
            
The site ID.
Note: Only visible if multisite functionality is active. - Costing Work Center
 - Costing Work Center
 - Detail Level
 - 
            
The detail level of the report.
 - Exclude Already Printed Orders
 - 
            
If this check box is selected, LN does not print the orders that were already printed.
 - Efficiency Variances
 - 
            
If this check box is selected, LN prints the efficiency variances.
 - Price Variances
 - 
            
If this check box is selected, LN prints the price variances.
 - Calculation Variances
 - 
            
If this check box is selected, LN prints the calculation office variances.
 - Transaction Date
 - 
            
If this check box is selected, you can specify the transaction date for which you want LN to print the production results.
 - Production Order
 - 
            
If this check box is selected, you can specify for which orders LN must print the production results.
 - Posted to Costing Work Center
 - 
            
If this check box is selected, LN prints the production results posted to the work center as well.
 - Posted to Production Order Calculation Office
 - 
            
If this check box is selected, LN prints the production results posted to the production order's calculation office as well.
 - Posted to Warehouse
 - 
            
If this check box is selected, LN prints the production results posted to the warehouse as well.
 - Main Item
 - 
            
If this check box is selected, LN does the analysis on main item level.
 - Cost Component
 - 
            
If this check box is selected, LN does the analysis on cost component level.
 - Cost Component Type
 - 
            
If this check box is selected, LN does the analysis on cost component level.
 - Posted to Project Calculation Office
 - 
            
If this check box is selected, LN prints the production results posted to the project's calculation office as well.