Use Up and Alternative Materials (tibom0150m100)
Use this session to view in which bill of material (BOM), this component is defined as use-up or alternative materials.
Field Information
- Alternative Item
 - 
            
The alternative material.
Note:The alternative item must be a non-configurable item.
For more information on procuring purchased configurable items, refer to
- Procuring configured items in Assembly Control - Master Data Setup
 - Procuring configured items in Assembly Control - BOM setup
 - Product variants - Purchased configurable items
 
Allowed values
If the item is a project item, the project must be equal to the project of the main item.
 - Main Item
 - 
            
The main item of which you want to maintain the use-up item or the alternative items.
 - Site
 - 
            
The site ID.
 - BOM Position
 - 
            
The component's BOM position number.
 - Position
 - 
            
The position number identifies the material.
 - Alternative Priority
 - 
            
The priority based on which the alterative material usage is determined. LN considers the alternatives based on specified priority.
Allowed values
- 
                  
Use up
This material is an outdated material ( use-up material) that must first be used up. - 
                  
1
The alternative that will be selected if the inventory of the standard material, and the use-up material, if any, is insufficient. - 
                  
2
The alternative that will be selected if the inventory of the standard material and the first alternative material, and the use-up material, if any, is insufficient. - 
                  
3, 4, 5, ...
Lower priority alternative materials. - 
                  
9
The lowest priority alternative material. 
 - 
                  
 - Effective Date
 - Expiry Date
 - 
            
expiry date
 - Net Quantity