Checking Use-up Material Definitions

In the Use Up and Alternative Materials (tibom0150m100) session you can checks the items, according to the following procedure:

  1. LN identifies the items that are part of the item range you entered and that are defined as a material of a bill of material (BOM) in the Job Shop List of Material (tibom3610m000) session.
  2. From these items, LN selects the items for which the Planner field in the Items - Ordering (tcibd2100m000) session names a planner that is part of the range of shop floor planners that you entered.
  3. From these items, LN selects the items for which a date is recorded in the Last Allowed Order Date field. (These items have been phased out or will be phased out).
  4. For each of these items, LN checks if the last allowed order date is not before the date in the Expiry Date field of the BOM line.
  5. If the last allowed order date is before the expiry date, LN checks if the BOM line has any alternative materials.
  6. If the last allowed order date is before the expiry date and no alternative materials are present for a BOM line, the BOM line is specified in an error report.