ATP priorities for multi-site

Previously, in a multi-site setup for a company, the ATP priorities could not be used in the PRP for planned PRP warehouse orders. All warehouses were checked, and planned orders could be created for warehouses that were unsuitable because, for example, they had another business purpose or were geographically distant.

In a multi-site setup, clusters can now be used based on the relevant ATP priorities from the ATP Priorities (tcmcs0168m000) session, which is linked to the Project Management Offices (tppdm0110m000) session.

In the Planning Parameters (tppss0100s000) and Generate Planned PRP Orders (tppss6200m000) sessions, you can specify whether to use ATP priorities, and the priority to consider. The settings in the Planning Parameters (tppss0100s000) session are used as defaults for the Generate Planned PRP Orders (tppss6200m000) session.