Contract flown down for claims

When claim lines are generated, additional information of, for example, linked sales orders and purchase orders is now copied to the claim lines. As is applicable for other objects in Service, if a project peg is available on the source object, any missing additional information is retrieved from the project contract and copied to the target object, unless a peg distribution is available.

For purchase orders and supplier claims, which can have a peg distribution instead of a single project peg, the priority of the project pegs in the peg distribution cannot be determined when copying additional information. Consequently, when supplier claims are generated, the additional information cannot be complemented through any of the project pegs in the peg distribution. Only if more pegs are added to the peg distribution later, the additional information from the related project contract can complement the additional information on the peg distribution’s parent object.