Specification of the project activity date when the actual work has started

If the new Set Actual Start Date based on Cost parameter is selected in the Project Planning Parameters (tppss0100s000) session, then the actual start date of a project activity can now be set, based on the actual cost that has been registered for an activity.

If selected, the actual start date is set as a result of registering and processing actual cost.