Material availability
Actual material lines
When a material line is added for a released activity, material availability is now verified. Previously, this had to be done manually, which often was forgotten.
Planned activities
Previously, the
option was only available for service orders and work orders. The option is now also available for planned activities.This option enables you to check the material availability for materials that are linked to the planned activity.
Service quotes
In the Service Quote Parameters (tsepp010m000) session, the Material Handling group has been added. These check boxes can be selected in this group:
- Create Planned Inventory Transactions: Planned inventory transactions are written if a quote line has a success percentage equal to or higher than a specified threshold.
- Check Material Availability: As for service orders, material availability can now also be checked for service quotes. To select this check box, the Create Planned Inventory Transactions must first be selected.
Project pegged inventory
Project pegged inventory is now taken into account when the material availability check is performed.