Orders in project schedule

n addition to production orders, you can now also display purchase orders, service orders, and work orders in the Project Schedule (tppss2700m000) session if these orders are linked to a project activity.

The Show Orders group has been added to select which orders are displayed. The Color Group field can be used to select a color from the Gantt Chart Colors (tccom5102m000) session, which can be used, for example, to distinguish the purchase orders from the production orders. Drill downs are available to the purchase order lines, service orders, and work orders. An indicator column in the Gantt shows if another project peg is present for the same purchase order line.

If changes are required, they must be made on the corresponding purchase, service, or work orders.