Project activity relationships

In the Project Schedule (tppss2700m100) session (Gantt), you can now establish activity relationships in the schedule itself. This can be done by selecting an activity or milestone and using the Create Successor Activity Relationship or Create Predecessor Activity Relationship options. By default, the Relationship Type field is set to Finish-to-Start and the Lag field to zero, but these fields can be changed before the new activity relationship is saved.

The options to create successor or predecessor relationships have also been added to the Activities (tppss2100m000) session.

If the Activity Relationships (tppss2510m000) session is started with a specific activity selected, the existing relationships for that activity are displayed. Previously, for the Activity Relationships (tppss2510m000) session, only an overview was available. Now, this session can also be started in a details mode to view all details of a planning relationship.