Peg distribution for cycle counting and adjustment orders
The implementation of the project pegging functionality impacts the cycle counting and adjustment processes due to inventory variances.
If project pegging is implemented, LN creates a peg distribution line before the cycle counting order or adjustment order is processed. The peg distribution line can also include a blank peg. The remaining quantity or the total quantity is then processed as unpegged.
After the cycle counting orders or adjustment orders are generated, the proposed peg distribution can be generated only if the warehouse is not a project warehouse. To generate a peg distribution for:
- A cycle counting order, use the Cycle Counting Order Line Peg Distribution (whinh5107m000) session.
- An adjustment order, use the Adjustment Order Line Peg Distribution (whinh5127m000) session.
If the peg distribution is not correct, the processing of the cycle counting order or adjustment order is discontinued and a message is displayed. If the peg distribution is incomplete, LN creates the peg distribution with the remaining data, which is saved in the:
- Cycle Counting Order Line Peg Distribution (whinh5107m000) session for cycle counting orders
- Adjustment Order Line Peg Distribution (whinh5127m000) session for adjustment orders