Viewing Plan Items - Optimized Lot Sizes
In the Plan Items - Optimized Lot Sizes (cprao3110m000) session, you can still modify the values of the following fields:
- Order Interval
- Lot Size (which, in fact is the economic order quantity)
- Old Lot Size
Use the Copy check box to select the optimized lot size settings and order intervals that LN must copy to the Items - Ordering (tcibd2100m000) session.
-
Select Copy Lot Sizes to Item Ordering Data (cprao3210m000) session.
on the appropriate menu to go to theThere you can define the plan items and the resources for which you want to copy the optimized lot sizes and order intervals to the Items - Ordering (tcibd2100m000) session.
- LN copies the optimized lot sizes to the Order Quantity Project field, and the order intervals to the Order Interval field in the Items - Ordering (tcibd2100m000) session.
- Select Optimize Lot Sizing (cprao3200m000) session, in which you can define a resource for which LN must compute the optimized lot sizes and order intervals for the items that are produced there. on the appropriate menu to go to the