Reporting Capacity CTP of Items by Resource
This session reports the capable-to-promise for all items that have this resource specified in the item's bill of critical capacities (BCC).
The reports contains the following information:
- The delivery period: the period for which you want to check the quantity of plan item that can be delivered.
- The cumulative capacity CTP of the specified resource in the specified period.
- The capacity CTP of the resource in the specified period.
- The cumulative ATP of the involved plan items in the specified period.
- The critical work center.
The reported CTP values are the sum of:
- The item's cumulative ATP
- The resource's cumulative capacity CTP divided by the capacity that is required for the item (according to the item's BCC)
Note: If the resource's
cumulative capacity CTP is negative, it is not taken into account.