Replanning
For orders that are already planned in the Planned Orders (cprrp1100m000) session, replanning can be performed.
To replan, click Planned Orders (cprrp1100m000) session. Replanning works the same as lead time planning, but it can be performed forward as well as backwards.
in theThe following calculations exist:
- Planning backward during the order planning run (normal planning)
- Replanning backwards
- Replanning forward
For forward planning, the start date is specified, while the planned finish date is calculated. Because the requirement date is not relevant in forward planning, item safety time, outbound lead-time, inbound lead time, and extra lead time are not planned.