Print Hours and Expenses History (bptmm2400m000)
Use this session to print a report of a selected range of hours transactions and expense history. LN maintains history for all the hours transactions that were entered in the hours accounting sessions. The history contains a record of the time that an employee spent on each transaction, and the costs incurred.
To print a report:
- Specify a selection range.
 - Cick to use the list of specific employees rather than specifying a range of employees.
 - Under Print Transactions For, select the appropriate check boxes to specify a range.
 - If required, click the appropriate button to further specify the range.
 - Under Report Options, select either of the following report
			 types: 
- 
                     
Consolidated Report
The report displays the labor time totals per labor type and day. - 
                     
Detailed Report
Every entered hours line is printed. 
 - 
                     
 - Select options as required.
 - Click .
 - In the Select Report dialog box, select the appropriate report layout.
 - Click OK.
 
Field Information
- Currency
 - 
            
home currency
From the Tools menu, choose Rotate Currency to switch home currencies.
 - 
            
- Consolidated Report
 - 
                     
Select the appropriate report option:
- 
                           
Consolidated Report
The report displays the labor time totals per labor type and day only for the selected transaction types. - 
                           
Detailed Report
Every entered hours line is printed only for the selected transaction types. 
 - 
                           
 - Entity in Report View
 - 
                     
If you choose to print a detailed report, and you select the Entity in Report View check box, you can group the report by entity type, for example, by project or by production order.
 - Cost Details
 - 
                     
If this check box is selected, data from the Cost Details (bptmm2501m000) session will be included in the report.
- 
                           
This option is only available if Detailed Report is selected in combination with any of the following check boxes:
- Project (PCS)
 - Production Order
 - Assembly
 
 - If this session is started from the Cost Details (bptmm2501m000) session, this option will be preselected.
 
 -