Job Scheduling Lines (ttaad5108m000)

Use this session to set up the calculation for the next execution data to run the job.

If multiple scheduling lines are defined, the next execution date is calculated for every scheduling line and the resulting earliest next execution time is used.

The result of the defined scheduling can be verified with the Calculate Execution Dates for Job (ttaad5408m000) session.

If the Calendar and Period fields of the job header are specified, then they are used for the scheduling.

Field Information

Job

Specify or select a job.

Description

A short description of the schedule to recognize the schedule on the overview.

Scheduling Type

Select a scheduling type.

Valid From

The start and end date and time of the schedule. Before the start date and after the end date the schedule is not used.

This field is required for the daily and weekly schedule, because it is used as the reference date to start the calculation. If the start date is not required and left blank, the schedule is valid.

Valid To

The end date is retrieved from the ‘End of Period’ of the job. A blank end date means that the schedule has an infinite validity.

Details

A display only field with some of the most important values depending on the type of the scheduling.

Between

The time frame in the day in which this job must be repeated. The start time is inclusive, the end time is exclusive. For example, when a job runs every 20 minutes starting at 08:00 and must end at 12.00 the last start time is 11:40. The next time would be 12:00 and this time is outside the range.

and

Specify an end time.

Run Time

Specify the start time to run the job.

Recurring Every

Every number of days. The default value is 1. If the number is higher than 1, for example 4, then the schedule runs on the 4th, 8th, 12th etc. day starting with the valid from date.

Run Time

Specify the start time to run the job.

Recurring Every

Every number of weeks. The default value is 1. If the number is higher than 1, for example 5, then the schedule runs on the selected days in the 5th, 10th, 15th etc. week starting with the valid from date.

Run Time

Specify the start time to run the job.

Specify if the job must run on specific Dates or Days.

All Months

If this check box is selected, the job must run every month. The individual months are disabled.