Activating SCM for a project VRC
- Log on to the LN server.
 - Start the Package VRCs (ttadv1511m000) session, and create a new (SCM) VRC. The new VRC must be derived from the project VRC.
 - Start the (De)activate SCM and Component Management by Package VRC (ttscm0501m000) session. The session shows a list of VRCs. Select the project VRC. On the appropriate menu, select . The Activate SCM and Component Management by Package VRC (ttscm0110s000) session starts.
 - Select the new SCM VRC and click .
 - To make the changes effective, log off and log on again.
 
          See "To use the Software Configuration Management system (SCM)" in the LN Web Help.