|   | To generate orders (TPOP)The Generate Orders (TPOP) (whinh2201m000) session is used to generate orders to replenish items
		for specific warehouses. LN generates the orders within an order horizon and based on the item and warehouse
		combination's safety stock and projected on hand. With the Generate Orders (TPOP) (whinh2201m000) session, you can only generate time-phased order point (TPOP) orders if: - You want to replenish at warehouse level.
 - The supply system for the item and warehouse combination is Time-Phased Order Point. You can specify the supply system in the Supply System field
		  of the Item Data by Warehouse (whwmd2110s000) session.
 - The items are of type Product, Purchased, or Manufactured. You can
		  specify the item type in the Item Type field of
		  the Item Defaults (tcibd0102m000) session.
 - The items are non- floor stock items. An
		  item is a non-floor stock item if the Floor Stock check
		  box on the Item - Warehousing (whwmd4600m000) session is cleared.
 
 Note - If you use the DEM Content Pack with Infor LN, consider
			 using the MPL0020 (Time Phased Order Supply (TPOP)) wizard to set up the supply of material using TPOP. You can execute this predefined
			 wizard from the Wizards by Project Model (tgwzr4502m000) session after
			 you specified the business function model for your company.
 - To replenish at item level, use the Generate Order Advice (SIC) (whina3200m000) session. For more information, refer to To generate order advice (SIC).
 
 In the Item Data by Warehouse (whwmd2110s000) session you must specify whether supply must take
		  place from a warehouse. To specify that supply must take place from a
		  warehouse, select the Supply from Warehouse check box. If this check box is cleared, supply will take place from: - A business partner if the item type is Purchased. You can specify
		  the business partner in the Buy-from Business Partner field of the Item Data by Warehouse (whwmd2110s000) session.
 - A work center if the item type is Manufactured. LN retrieves the work
		  center from Manufacturing.
 -  
If the item type is Product,
				the supply source of the item displayed in the Actual Supply Source field of the Items (tcibd0501m000) session determines from where supply takes place: - A business partner if the supply source is Purchase.
 -  
A work center if the supply source is: - Shop Floor
 - Repetitive
 - Assembly
 - Distribution
 
  
  
 Order horizon Before LN generates orders, it determines the order horizon for which the replenishment must take
		place. However, this calculation does not take into account the actual
		calendar. If LN determines the order horizon, LN considers that a week has seven days, and a day has 24 hours. LN determines the
		order horizon as follows: order horizon = current date + (total lead time * order horizon factor) + order horizon constant  LN determines the total lead time based on the warehouse and item combination's
		supply type. However, LN determines the total lead time without taking into account the
		calendars. If supply takes place from: - A business partner, LN retrieves the Supply Time from
		  the Items - Purchase Business Partner (tdipu0110m000) session.
 - A work center, LN retrieves the Order Lead Time from the Item - Production (tiipd0101m000) session.
 -  
A warehouse, LN retrieves and adds up the following lead times: -  Inbound Lead Time from the Item Data by Warehouse (whwmd2110s000) session.
 -  Outbound Lead Time from the Item Data by Warehouse (whwmd2110s000) session.
 - Transport time between the ship-from's address and the
				ship-to's address, based on a relevant distance table (if available) in the Distance Table by City (tccom4137s000) session or in the Distance Table by ZIP Code/Postal Code (tccom4138s000) session. From which of these two
				sessions the transport time is retrieved depends on the value of the Usage Distance Tables field on the COM Parameters (tccom0000s000) session.
 
  
 Note In the Generate Orders (TPOP) (whinh2201m000) session, you can overrule any of the order
		  horizon data that is defined under TPOP Order Horizon in the Inventory Analysis Parameters (whina0100m000) session. Note You can specify a seasonal pattern for at most one year. All
		seasonal patterns start at January 1, after which they are repeated during the
		year according to the number of periods. In the Item Data by Warehouse (whwmd2110s000) session you can specify: - The base reorder point in the Reorder Point field.
 - The base safety stock in the Safety Stock field.
 - The seasonal pattern for safety stock in the Seasonal Pattern for Safety Stock field.
 
 To generate orders (TPOP) With the Generate Orders (TPOP) (whinh2201m000) session, LN generates an order
		for each requirement within the order horizon. The ordered quantity depends on: - The safety stock. (If seasonal patterns apply, the safety stock
		  defined at the end of the order horizon is taken into account.)
 - The projected on hand.
 -  
The replenishment settings defined in the following
				sessions: - Item Data by Warehouse (whwmd2110s000), Replenishment tab.
 - Items - Purchase Business Partner (tdipu0110m000), Ordering tab.
 
  
 The kind of order that is generated for the item and warehouse
		combination depends on the source from which supply takes place: | Supply takes place from... | LN generates... |  | Warehouse | Warehousing order with order origin Transfer (Manual) for the warehouse that is specified in the Supply Warehouse field of the Item Data by Warehouse (whwmd2110s000) session. |  | Business
				partner | Purchase order for the
				buy-from business partner that is specified in the Buy-from Business Partner field of the Item Data by Warehouse (whwmd2110s000) session. |  | Work center | Production order. |  
   Note Planned inventory transactions that are excluded from
		  planning, that is, for which the Exclude from Planning have quantity 1, are not taken
		  into account for TPOP runs. To determine the requirement date The requirement date is the date on which the projected on hand
		drops below the safety stock, and coincides with the current date. To determine the actual requirement date, LN takes into account
		the actual calendar. If the requirement date is not available according to the
		actual calendar, LN looks backwards for the first available date/time before the requirement date. LN sets the first
		available date/time as the actual requirement date. To determine the planned receipt date LN determines the planned receipt date by planning backwards from the requirement
		date and taking into account the actual calendar. LN determines the planned receipt date as follows: planned receipt date = planned requirement date - outbound lead time - inbound lead time - item safety time - supplier safety time  LN only takes into account: - The supplier safety time if supply takes place from a business
		  partner.
 - The outbound lead time and the item safety time if the
		  requirement is caused by a planned inventory transaction.
 
 LN retrieves: - The outbound lead time from the Item Data by Warehouse (whwmd2110s000) session.
 - The inbound lead time from the Item Data by Warehouse (whwmd2110s000) session.
 - The item safety time from Safety Lead Time field of the Item Data by Warehouse (whwmd2110s000) session.
 - The supplier safety time from the Safety Time field
		  of the Items - Purchase Business Partner (tdipu0110m000) session.
 
 To take into account the actual calendar When LN determines the requirement date, the planned receipt date, and
		  the planned delivery date, it takes into account the actual calendar.
		  Therefore, LN first
		  searches for a calendar in the following order: - The warehouse's calendar.
 - If the warehouse's calendar is not specified, the company's
		  calendar.
 
 LN bases the actual calendar on the found calendar code and the availability type. LN determines the requirement date, the planned receipt date, and
		the planned delivery date based on the actual calendar. Before the calendar's start date and after the calendar's end
		date, the standard calendar applies. When LN determines the requirement date, the planned receipt date, and the planned
		delivery date, and if the lead times are expressed in hours, LN takes into account
		all the time that is available on a day according to the actual calendar.
		However, if the lead times are expressed in days, LN considers a day a
		whole day if the actual calendar indicates that time is available on that day. Note - You can view the actual calendar in the Calendar Working Hours (tcccp0120m000) session.
 - You can define the availability type on the Storage Inspection tab of the Warehouse Master Data Parameters (whwmd0100s000) session.
 
 Important If the Use Item Ordering Data check box in the Item Data by Warehouse (whwmd2110s000) session is selected, LN retrieves the
		  following data from the Item - Ordering (tcibd2100m000) session instead of from the Item Data by Warehouse (whwmd2110s000) session: -  Seasonal Pattern for Safety Stock
 -  Reorder Point
 -  Safety Stock
 
 Example To replenish items for each warehouse if supply takes place
		from a warehouse. - Current date/time: Wednesday, January 3/1:30:00.
 - Inventory on hand on current date (in pieces): 18.
 - Order horizon factor: 3.
 - Order horizon constant (in days): 15.
 - Inbound lead time (in hours): 4.
 - Outbound lead time (in hours): 4.
 - Transport time (in days): 2.
 - Item safety time (in days): 2.
 - Supplier safety time (in days): 2.
 - Base safety stock (in pieces): 10.
 - Seasonal pattern for safety stock has period type: Week.
 - Number of periods: 4.
 
 The warehouse's actual calendar is available from Monday
		through Friday each week and has an 8:00:00 start time and a 17:00:00 end time. LN determines the order horizon as follows: - Order horizon = current date + [(inbound lead time + outbound
		  lead time + transport time) * order horizon factor] + order horizon constant.
 - Order horizon = January 3/1:30:00 + [(4 hours + 4 hours + 2
		  days) * 3] + 15 days.
 - Order horizon = January 3/1:30:00 + [56 hours x 3] + 360 hours.
 - Order horizon = January 3/1:30:00 + 528 hours = January
		  25/1:30:00.
 
 The seasonal pattern for safety stock is as follows, with the
		resulting safety stock and reorder point: | Period | Start date period | Seasonal pattern factor | Safety stock | 
|---|
 | Period 1 | January 1/0:00:00 | 1.5 | 15 |  | Period 2 | January 8/0:00:00 | 2.0 | 20 |  | Period 3 | January 15/0:00:00 | 2.5 | 25 |  | Period 4 | January 22/0:00:00 | 1.5 | 15 |  
   Planned inventory transactions: - January 11/18:00:00 planned issue of 9.
 - January 23/11:30:00 planned issue of 8.
 
 The projected on hand before planning the replenishment is as
		follows: | Date | Projected on hand | 
|---|
 | January 3 | 18 |  | January 11 | 9 |  | January 23 | 1 |  
   If you replenish items for each warehouse, based on the data
		  just provided, the results are as follows: - On Monday, January 8/0:00:00, the safety stock exceeds the
		  projected on hand with two items. Therefore, LN generates a
		  warehousing order to replenish two items. Because Monday, January 8/0:00:00, is
		  not available according to the actual calendar, LN sets Friday, January
		  5/17:00:00, as the requirement date. To determine the planned receipt date, LN subtracts four hours
		  inbound lead time from the requirement date. As a result, the planned receipt
		  date is Friday, January 5/13:00:00. Because a warehousing order is generated, LN also determines the
		  planned delivery date by subtracting two days transport time from the planned
		  receipt date. As a result, the planned delivery date is Thursday, January
		  4/8:00:00.
 - On Thursday, January 11/18:00:00, the projected on hand
		  decreases and falls below the safety stock with nine items caused by a planned
		  inventory transaction. As a result, LN generates a warehousing order to replenish
		  nine items. Because Thursday, January 11/18:00:00, is not available according
		  to the actual calendar, LN sets Thursday, January 11/17:00:00, as the
		  requirement date. To determine the planned receipt date, LN subtracts four hours
		  outbound lead time, four hours inbound lead time, and one day item safety time
		  from the requirement date. As a result, the planned receipt date is Thursday,
		  January 11/8:00:00. Because a warehousing order is generated, LN also determines the
		  planned delivery date by subtracting two days transport time from the planned
		  receipt date. As a result, the planned delivery date is Tuesday, January
		  9/8:00:00.
 - On Monday, January 15/0:00:00, the safety stock exceeds the
		  projected on hand with five items. Therefore, LN generates a
		  warehousing order to replenish five items. Because Monday, January 15/0:00:00,
		  is not available according to the actual calendar, LN sets Friday, January
		  12/17:00:00, as the requirement date. To determine the planned receipt date, LN subtracts four hours
		  inbound lead time from the requirement date. As a result, the planned receipt
		  date is Friday, January 12/13:00:00. Because a warehousing order is generated, LN also determines the
		  planned delivery date by subtracting two days transport time from the planned
		  receipt date. As a result, the planned delivery date is Thursday, January
		  11/8:00:00.
 - On Monday, January 22/0:00:00, the safety stock decreases to 15
		  items while the projected on hand is 25 items. As a result, no replenishment is
		  needed and LN does not
		  generate a warehousing order.
 - On Tuesday, January 23/11:30:00, the projected on hand
		  decreases with eight items. Because the projected on hand does not fall below
		  the safety stock, LN does
		  not generate a warehousing order.
 
 The projected on hand after planning the replenishment is as
		follows: | Date | Projected on hand | 
|---|
 | Wednesday January 3 | 18 |  | Friday January 5/13:00:00 | 20 |  | Thursday January 11/8:00:00 | 29 |  | Thursday January 11/17:00:00 | 20 |  | Friday January 12/13:00:00 | 25 |  | Tuesday January 23/11:30:00 | 17 |  
      |   |