|   | Determination of calendar correctionWhen LN determines the planned delivery date and the planned receipt date
		  in the Warehousing Orders (whinh2100m000) session, LN takes into account
		  the calendars of the ship-from data and the ship-to data to determine the
		  required calendar correction. LN determines the calendar correction for ship-from data and ship-to
		  data in the same way. The calendar correction determination only differs in the
		  following way: - If the calendar correction must be determined for the ship-from
		  data, LN uses the Ship-from Code.
 - If the calendar correction must be determined for the ship-to
		  data, LN uses the Ship-to Code.
 
 To be able to add a calendar correction, LN searches for a
		  calendar as follows: - If the Ship-from Code or the Ship-to Code is a warehouse, LN searches for a
		  calendar in the following sequence: the address' calendar, then the warehouse's
		  calendar, and then the company's calendar. In all other cases, LN uses the address'
		  calendar. If LN cannot
		  find any calendar, a calendar correction does not take place.
 -  
If a calendar is found, LN searches for the
				actual calendar based on:  - LN determines the calendar correction based on the actual calendar's start time
		  and end time.
 
 Note - You can view the actual calendar in the Calendar Working Hours (tcccp0120m000) session.
 - You can define the availability type in the Warehouse Master Data Parameters (whwmd0100s000) session.
 
    |   |