Project Cost Objects and Standard Costs Objects (Resources)
You can use this option to export the project cost objects and
standard costs objects (Resources) to the ESP.
Export project cost objects and standard costs objects
(Resources) data
Cost objects are included in the export only if the cost type is
selected and if the Used in Schedule option is selected in the respective
cost object sessions. Using these options, it is possible to prevent that cost
objects that are not required are included in the XML to ensure that the files
are manageable.
This data is exported to the ESP:
- Identification information specified in the Transfer Resource group box such as the resource type and cost
object.
- Scheduling information such as the Calendar.
- Costing information such as the sales price and cost
rate.
- Additional information such as employee information, user
account, and email address from the Employees (tccom0501m000) session.
Restrictions for the export of Cost Objects and other
resources:
| Cost Object/Resource | Restriction
in Cost Object | Restriction Session option “Transfer
Resources” |
| Employees | Used in Schedule =
Yes | Employees = Yes |
| Trade Group | Not
Applicable | Trade Group = Yes |
| Standard
Labor | Used in Schedule = Yes | Labor Cost Object =
Yes |
| Project Labor | Related to selected
project | Labor Cost Object = Yes |
| Standard
Equipment | Used in Schedule = Yes | Equipment =
Yes |
| Project Equipment | Related to selected
project | Equipment = Yes |
| Standard
Subcontracting | Used in Schedule = Yes | Subcontracting =
Yes |
| Project Subcontracting | Related to selected
project | Subcontracting = Yes |
| Standard Sundry
Costs | Used in Schedule = Yes | Sundry Costs =
Yes |
| Project Sundry Costs | Related to selected
project | Sundry Costs = Yes |