To calculate overheadsLN calculates the overheads for all the application bases, based on the postings in projects and the defined overhead application bases. Step 1. Select the fiscal period, of the current year, for which overhead must be calculated from the options given in the fiscal period selection. Following are the possible values:
Step 2. Use the Exclude checkbox to specify the data that must be excluded from the calculation. Step 3. Select the level at which overheads must be calculated. Following are the possible values.
Step 4. Specify the range of data for which overheads must be calculated. Step 5. Select the Logging checkbox in the Options tab to save the overhead calculation log file after calculation. Step 6. Click Calculate. Step 7. Review the calculations in the Calculate and Apply Overhead (tpppc6120m000) session.
| |||